£32m Ardleigh Green Bridge Update

 

bridger

Lifting the service bridge into position

Works to replace the Ardleigh Green Bridge on the A127 are expected to last until late 2017.

As part of the advance works currently underway, the service bridge was constructed and then lifted into place overnight (see picture) on Saturday 12 and Sunday 13 December 2015.

During the main bridge replacement works (mid-2016 to end-2017) only two lanes of traffic will be operational (one lane in each direction).

For more information about road closures and stages of completion, please click  HERE