With regard to our previous post concerning the Gallows Corner Flyover replacement, Transport for London (TfL) have announced that the full reopening of the flyover will be delayed past the recently announced opening date of the end of April 2026. This is apparently due to further issues that Essex and Suffolk Water (ESW) are experiencing with their works at the site.

Upminster and Cranham Residents’ Association (UCRA) councillors are extremely frustrated with this latest delay, as residents will be, especially as this means that a project originally scheduled to take four months, will now be running in excess of eight months overdue. We will keep you updated when we have further news.

To view the TfL statement on the latest delay, visit the Gallows Corner Flyover works webpage.